Brainerd Demolition

Project Statistics:
  • Removal of 3 #6 heating oil tanks (approximately 60000 gallon each)
  • Recycled 5 million pounds of steel
  • Crushed approximately 20000 yards of concrete
  • Demolition of building # 1 Administration building (73265 Sq Ft)
  • Demolition of building #2 Maintenance building (158596 Sq Ft)
Project Details

Work consisted of the complete demolition and disposal of the former administration building and the maintenance building on the Brainerd Regional Human Services Center Campus. In order to complete the demolition, removal of the contents in the building was necessary which included the removal of 2 hydraulic and 2 traction controlled elevators.  Other items performed were demolition of the tunnel systems which tied those buildings to the rest of the campus.  To complete the project, site restoration, topsoil placement, seeding and turf establishment will take place in the spring of 2013.